West Kowloon
Drainage Improvement,
Stage 3 Phase 1 Works
( Yau Ma Tei Area)

西九龍雨水排放系統改善計劃
第三階段第一期
(油w地區
)

Background
The Drainage Services Department awarded a HK$280 million contract to China Road and Bridge Corporation (China Road & Bridge) on 13 March 2002 for undertaking the ☆West Kowloon Drainage Improvement, Stage 3 Phase 1 Works∣ in Yau Ma Tei. Under the contract, China Road & Bridge is required to construct about 6 km of drain pipes with diameters ranging from 300 mm to 2,100 mm, and about 3.1 km of single-cell or two-cell box culverts of cell size up to 4,800 mm x 2,500 mm in Yau Ma Tei and Sham Shui Po.

China Road and Bridge, in turn, engaged L&M to be the specialist contractor to construct about 97.8 m long drain pipes from Man Cheong Street to Saigon Street, crossing Ferry Street and Wai Ching Street.

Construction Works
Started the works in December 2003, L&M adopts the pipe jacking with hand shield method to install the drain pipes under the busy streets with congested underground utilities and heavy pedestrian traffic. According to Mr. Tai Hok Hoi, Manager of L&M㏒s Geotechnical Division, using the hand shield pipe jacking method, instead of slurry boring shield machine, is to avoid any damage to the congested underground utilities which include cable fibre, the sewer and box culvert, the sheetpiles and so on.

The sequence of the works is as follows:
1. Construction of jacking pit
2. Ground treatment (to ensure the jacking pit being reasonable dry)
3. Fabrication of entrance ring and cut opening of sheet pile wall
4. Horizontal grout to stabilize soil ahead pipe jacking
5. Pipe jacking
6. Construction of receiving pit

Challenges & Difficulties
Unforeseen underground condition poses a great challenge on L&M. Initially, L&M expected that the works could be completed within four months. However, the existing underground utilities and old structures, especially the sheetpiles running 25 m long under Wai Ching Street, extend the work time to more than six months. Underground investigation had to be conducted before commencing the project. Hand digging and horizontal grouting are also required to take extreme care about the existing underground utilities during the course of pipe jacking. Especially the cable fibre was protected and supported by underpinning.

L&M completed the 97.8m long pipelines in late June 2004. The construction peak of the project was from December 2003 to June 2004 with around 12 workers involved in the works.

背景
在二零零二年三月十三日,中國路橋(集團)總公司<下簡稱中國路橋>獲得渠務署一份價值二億八千萬港元的工程合約,負責承造西九龍雨水排放系統改善計劃第三階段第一期油w地區的工程。根據合約規定,中國路橋需要在油w地和深水鶢潃茼a區建造長約六公里的排水管,直徑介乎三百至二千一百毫米,以及建造長約3.1公里的單孔或雙孔箱形暗渠,面積約4800x2500毫米。

林麥地工專業有限公司下簡稱林麥地工,受中國路橋委托擔任是項工程的專業承造商,鋪建一段長約97.8公里的排水管,由文昌街伸延至西貢街,途經渡船街及偉晴街。

建造方法
林麥地工在2002年12月動工,採用手作護盾頂管法於繁忙街道下建造排水管,這些街道的地下佈滿管線,而路面又滿是行人和車輛。據林麥地工土木工程部經理戴學海先生表示:公司之所以採用手作護盾頂管法而棄用液壓平衡護盾鑽挖法,是為免破壞眾多的地下管線,當中包括電纜光纖、污水管、箱形暗渠及板樁等。

鋪建排水管的施工步驟概括如下:

  1. 建造出發井;
  2. 地層處理確保出發井保持一定的乾爽;
  3. 裝配入口圈環及開切板樁牆的缺口;
  4. 以水平灌漿法加固泥土;
  5. 施行頂管法;
  6. 建造到達井。

挑戰和困難
林麥地工面對的最大挑戰是地下情況不昨朗。最初,林麥地工預計可在四個月內完成工程,但得悉地下佈滿密密麻麻的管線和舊結構物後,尤其在偉靖街下長約25米的板樁牆,工程便需順延六個月後才完成。另外,在工程展開前,林麥地工需進行地下勘測;而在施行頂管法期間,林麥地工又需要採用手挖及水平灌漿,以小心保護現有的地下管線。林麥地工更在頂管外加置基礎來保護及支M電纜光纖。

長約97.8米的管道於2004年6月底建成。工程的建築高峰期由2003年12月至翌年6月,期間約有12名工人趥P施工。

 

<The information and photos are provided by L&M Foundation Specialist Ltd.>
以上資料及相片由林麥地工專業有限公司提供